Work:
Parsons: PG&E Hydro Power Generation Capital Improvement Program
Paradise, CA
Sep 2009 to May 2012
Outage Manager, Project Manager, Chief Estimator
Parsons: ThyssenKrupp Steel Finishing Mill. Hot Strip Mill
Calvert, AL
May 2008 to Aug 2009
Area Construction Manager, Chief Estimator, Planner
Parsons Construction Group - Industrial Division
Sumner, WA
Apr 2007 to May 2008
Estimator, Business Developement
Parsons Construction Group - Equa-Chlor 200TPD Chlor-Akili Plant
Longview, WA
Oct 2004 to Mar 2008
EPC Project Manager (Capture, Execution & Claims Manager)
PCG - Industrial - Tacoma Water Chemical Treatment Facility
Sumner, WA
Nov 2003 to Oct 2004
Estimator, Project Manager
Dillon Mechanical, Inc.
Puyallup, WA
Dec 1997 to Jun 2004
President - Plumbing, Mechanical, Process Piping Contractor
Matsushita Semiconductor - Fab D
Puyallup, WA
Jun 1997 to Nov 1997
Owners Representative, Start-up & Commissioning Coordinator
Harder Mechanical - Matsushita Fab D
Puyallup, WA
Jul 1996 to Jun 1997
Tool Hook-Up Project Engineer
RM Mechanical, Inc. - Micron Semiconductor
Boise, ID
Jun 1991 to Jul 1996
Senior Project Manager
University Mechanical - Semiconductor Cleanrooms, Health Care & Commercial
Riverside, CA
May 1985 to Sep 1990
Process & Mechanical Project Engineer, Detailer
FT Andrews Consulting Mechanical Engineers
Fullerton, CA
1981 to 1985
Senior Designer, Department Manager
20th Century Plumbing
Orange, CA
1977 to 1979
Plumbing Estimator, Detailer